Production Management

1. Function Overview

The Production Management module is the core module of the MES system, covering the entire process from production planning to production execution. It achieves digitalization, transparency, and intelligence of the production process.

Core Functions:

Function Description
Production Planning Production plan formulation and breakdown
Work Order Management Work order creation, approval, release, and change
Reporting Management Production reporting and completion confirmation
Production Monitoring Real-time production progress monitoring
Material Flow Material release, picking, and semi-finished product flow
Production Reports Production data statistics and analysis

2. Production Planning Management

2.1 Production Plan Types

Plan Type Description Time Range
Annual Plan Annual production outline 1 year
Monthly Plan Monthly production plan 1 month
Weekly Plan Weekly production schedule 1 week
Daily Plan Daily production dispatch 1 day
Emergency Plan Rush order, change plan Immediate

2.2 Production Plan Sources

Plan Generation Methods:

Source Description Automation Level
Sales Order Generated from sales orders Semi-automatic
Forecast Order Generated from forecast data Semi-automatic
Inventory Replenishment Generated when inventory below safety level Automatic
Manual Creation Manually created plan Manual

2.3 Plan Balance and Breakdown

Plan Balance Process:

┌─────────────┐    ┌─────────────┐    ┌─────────────┐    ┌─────────────┐
│Demand Plan  │───▶│Capacity Check│───▶│Plan Adjustment│───▶│Plan Confirmation│
└─────────────┘    └─────────────┘    └─────────────┘    └─────────────┘

Capacity Assessment Factors:

Assessment Item Assessment Content
Equipment Capacity Whether equipment capacity meets requirements
Material Capacity Whether materials are available
Personnel Capacity Whether personnel are sufficient
Tooling Capacity Whether tooling fixtures are ready
Environmental Capacity Whether production environment meets requirements

3. Work Order Management

3.1 Work Order Types

Work Order Type Description Trigger Method
Production Order Normal production order Plan triggered
Rework Order Rework production order Quality issue triggered
Material Supplement Order Material supplement order Scrap triggered
Trial Order Trial production order R&D triggered
Emergency Order Emergency rush order Ad-hoc triggered

3.2 Work Order Status Flow

Status Flow Diagram:

┌────────┐    ┌────────┐    ┌────────┐    ┌────────┐    ┌────────┐
│Pending │───▶│Created │───▶│Approved│───▶│Released│───▶│In      │
│Draft   │    │        │    │        │    │        │    │Production│
└────────┘    └────────┘    └────────┘    └────────┘    └────────┘
     │                                                          │
     │                                                          ▼
     │                                                    ┌────────┐
     │                                                    │Completed│
     └────────────────────────────────────────────────────▶│        │
                                                          └────────┘

Status Description:

Status Description Available Operations
Pending Draft Plan being formulated Edit, Delete
Created Plan completed Submit for approval, Edit
Approved Approved Release
Released Released to production line Start production
In Production Production in progress Reporting, Pause
Completed Production completed Receiving, Close
Closed Work order closed View
Cancelled Work order cancelled View

3.3 Work Order Creation

Creation Steps:

  1. Go to [Production Management] → [Work Order Management]
  2. Click [New Work Order]
  3. Select product
  4. Fill in work order information:
    • Production quantity
    • Planned start/end date
    • Planned production line
    • Priority
  5. System automatically calculates material requirements
  6. Save work order

[Note] Ensure product BOM and routing are maintained before creating work order.

3.4 Work Order Information

Work Order Basic Information:

Field Description Required
Work Order No. Unique work order identifier
Product Code Product to produce
Product Name Product name
Production Quantity Planned production quantity
Qualified Quantity Qualified product quantity -
Defective Quantity Defective product quantity -
Planned Start Date Planned start date
Planned End Date Planned end date
Actual Start Date Actual start date -
Actual End Date Actual end date -
Priority Work order priority
Work Order Status Current status System auto

Work Order Related Information:

Related Item Description
Sales Order Related sales order
Customer Info Customer information
BOM Version BOM version used
Process Version Process version used

3.5 Work Order Approval

Approval Process:

  1. Work order creator submits for approval
  2. Approver receives approval task
  3. Review work order information
  4. Check material availability
  5. Check capacity status
  6. Approve or reject

[Tip] Work order quantity and planned dates can be adjusted during approval.

3.6 Work Order Release

Release Conditions:

Condition Check Item Description
Complete Information All required fields filled
Approved Work order status is approved
Valid BOM BOM is approved and effective
Valid Process Routing is approved and effective
Materials Available Required materials in stock
Line Available Production line is available

Release Steps:

  1. Select approved work order
  2. Click [Release] button
  3. System performs availability check
  4. Availability check passed
  5. Confirm release information
  6. Work order status changes to "Released"

[Note] If availability check fails, materials need to be replenished or work order adjusted first.

3.7 Work Order Change

Change Types:

Change Type Description Impact
Quantity Adjustment Increase/decrease production quantity Affects material requirements
Plan Adjustment Adjust planned dates Affects scheduling
Line Change Change production line Affects scheduling
Process Adjustment Adjust process sequence Affects routing
Emergency Rush Adjust work order priority Affects scheduling

Change Process:

Change Request → Change Approval → Change Execution → Change Confirmation

[Tip] Work order changes during production need to be handled carefully as they may affect ongoing production operations.

4. Reporting Management

4.1 Reporting Types

Reporting Type Description Timing
Start Reporting Process starts operation At process start
Completion Reporting Process completes operation At process completion
Exception Reporting Process abnormally paused When exception occurs
Shift Reporting Shift handover record At shift handover

4.2 Reporting Process

Process Reporting Flow:

Start Reporting → Process Operation → Completion Reporting → Next Process

Detailed Flow:

┌──────────┐    ┌──────────┐    ┌──────────┐    ┌──────────┐
│Start     │───▶│Operation │───▶│Completion│───▶│Quality   │
│Reporting │    │In Progress│    │Reporting │    │Inspection│
└──────────┘    └──────────┘    └──────────┘    └──────────┘
                                                            │
                    ┌──────────────────────────────────────┘
                    │
                    ▼
              ┌──────────┐
              │Process   │
              │Transfer  │
              └──────────┘

4.3 Start Reporting

Operation Steps:

  1. Go to [Production Management] → [Reporting Management]
  2. Select work order ready to start
  3. Select process
  4. Fill in start information:
    • Start time
    • Operator
    • Equipment selection
  5. Submit start report
  6. System records start time

[Tip] After start reporting, the system locks the process to prevent duplicate starts.

4.4 Completion Reporting

Operation Steps:

  1. Select started work order
  2. Select process
  3. Fill in completion information:
    • Completed quantity
    • Qualified quantity
    • Defective quantity
    • Defect reason (if any)
    • Operation time
    • Material consumption (if needed)
  4. Submit completion report
  5. System automatically triggers quality inspection (if inspection point configured)

Completion Reporting Information:

Field Description Required
Completed Quantity Quantity completed this time
Qualified Quantity Qualified product quantity
Defective Quantity Defective product quantity -
Defect Reason Description of defect reason -
Operation Time Actual operation time
Material Consumption Quantity of materials consumed -

4.5 Reporting Data

Reporting Record Information:

Data Item Description
Reporting Time Reporting operation time
Reporting Type Start/Completion/Exception
Work Order No. Related work order
Process No. Related process
Operator Person performing operation
Equipment No. Equipment used
Reporting Quantity Reported quantity
Qualification Rate Qualified quantity/Reported quantity
Operation Time Actual operation time

5. Production Monitoring

5.1 Monitoring Content

Real-time Monitoring Data:

Monitoring Item Description Update Frequency
Work Order Progress Completion status of each work order Real-time
Process Progress Completion status of each process Real-time
Production Statistics Daily/Shift production volume Real-time
Defective Rate Defective product ratio Real-time
Equipment Status Equipment running status Real-time
Personnel Status Operator status Real-time

5.2 Monitoring Dashboard

Production Dashboard Display:

┌─────────────────────────────────────────────────────────────┐
│                    Production Monitoring Dashboard          │
├─────────────────────────────────────────────────────────────┤
│                                                             │
│  Today's Production Overview:                               │
│  ┌──────────────┐ ┌──────────────┐ ┌──────────────┐         │
│  │  Plan Output │ │ Actual Output│ │  Achievement │         │
│  │   10000     │ │   9520      │ │   95.2%    │         │
│  └──────────────┘ └──────────────┘ └──────────────┘         │
│                                                             │
│  Production Line Status:                                    │
│  ┌─────────────────────────────────────────────────────┐   │
│  │ SMT-A Line ████████████░░░░  80%    Running         │   │
│  │ SMT-B Line ██████████████░░  85%    Running         │   │
│  │ Assembly-A ██████████░░░░░░  60%    Running         │   │
│  └─────────────────────────────────────────────────────┘   │
│                                                             │
└─────────────────────────────────────────────────────────────┘

5.3 Process Flow Control

Flow Rules:

Flow Type Description Configuration Requirement
Sequential Flow Operations in defined sequence Routing definition
Parallel Flow Multiple processes simultaneously Routing definition
Conditional Flow Process selection based on conditions Flow condition configuration

Process Start Conditions:

Condition Item Check Content
Previous Process Complete Whether previous process completed
Materials Available Whether materials ready
Equipment Ready Whether equipment idle
Personnel Ready Whether operators ready

6. Material Flow

6.1 Material Release Management

Release Process:

Material Request → Warehouse Preparation → Scan Release → System Confirmation

Release Methods:

Method Description Application Scenario
By Work Order Release based on work order BOM Batch production
By Process Release based on process requirements Multi-process production
By Line Batch release to production line Continuous production
Auto Release System automatically controls release Automated production line

6.2 Material Consumption Record

Consumption Data:

Data Item Description
Material Code Material consumed
Material Batch Material batch number
Consumption Quantity Quantity consumed this time
Consumption Time Consumption time
Related Work Order Related work order
Related Process Related process
Consumption Type Actual consumption/Scrap

6.3 Work In Process (WIP) Management

WIP Monitoring:

Monitoring Item Description
WIP Work Order Count Number of work orders in production
WIP Process Count Number of processes in progress
WIP Quantity Quantity in progress at each process
Flow Time Flow time at each process
Accumulation Status Accumulation status at each process

7. Production Statistics and Analysis

7.1 Production Reports

Report Type Description Target User
Daily Production Report Daily production statistics Workshop Supervisor
Monthly Production Report Monthly production statistics Production Manager
Work Order Statistics Work order execution statistics Planner
Output Statistics Output completion statistics Production Supervisor
Quality Statistics Production quality statistics Quality Supervisor

7.2 Production Indicators

Core KPI Indicators:

Indicator Calculation Formula Description
Output Achievement Rate Actual Output/Plan Output × 100% Target: ≥100%
Production Qualification Rate Qualified Quantity/Total Quantity × 100% Target: ≥98%
Labor Utilization Rate Actual Working Hours/Available Hours × 100% Target: ≥85%
Process Flow Time Average flow time at each process Shorter is better
WIP Turnover WIP Quantity/Daily Output Target: 3-5 days

7.3 Production Analysis

Analysis Dimensions:

Analysis Dimension Analysis Content
Capacity Analysis Capacity utilization, bottleneck analysis
Efficiency Analysis OEE analysis, efficiency improvement potential
Quality Analysis Defective product analysis, quality trend
Material Analysis Material consumption analysis, over-consumption analysis
Labor Analysis Working hours utilization analysis, overtime analysis

End of Production Management